Suppose your client has two proposals from your company on their desk. Your office has offered standard drafting at $120 an hour. Another office has offered them the same service for $100 an hour. The client rings you and asks a fairly reasonable question. “What do I get for the extra $20?” What would you tell them?
Problem: The client sees both proposals
I have seen this happen. Two departments in a company I worked for bid on similar projects for the same client. We offered significantly different hourly rates for similar services. The client spotted the difference and tried to negotiate the rates in our other proposal down.
You might think we won the cheaper of the two jobs. We didn’t win either of them. The client had decided they couldn’t trust us. By then, whether we were prepared to come down on price was beside the point.
It’s easy to see how you could end up in that position. If I’m preparing a bid, the first place I might look is the last proposal our office sent for similar work. The project manager in another office might do exactly the same thing. My starting point could be this year’s approved rates. Theirs could be a rate someone discounted last year to win six months of drafting work. Both spreadsheets might just say “standard drafting”.
The client has no reason to know any of that. As far as they are concerned, they asked one company to price two jobs. If the contract rates look arbitrary, what confidence can they have in the rest of our estimate?
Solution: Check what your company has already offered
Start with the rates agreed with that client
Before pricing the next job, check whether your company already has an agreement with the client. It might set hourly rates for particular staff grades, say which expenses you can charge separately, or specify when a rate increase takes effect. Check whether it covers the work you are bidding for. If it does, use it as your starting point.
Then find out who else is bidding for work with that client. A register of submitted proposals is handy, but it won’t show you the bid someone is still writing. A quick call to the person who looks after the client account could have put our two bid managers in touch while there was still time to do something about it.
Give people one place to find current contract rates
Keep an approved schedule of rates where project managers in every office can find it. Give it an effective date, identify who maintains it and show where any client-specific rates are kept. If you approve a discount for one job, record which job it covers and why you offered it. The next person preparing a bid needs to know whether they can offer it again.
Give each proposal a validity period, particularly around your annual rate review. If your rates go up on 1 July, someone needs to check the proposal you issued in June and whether the client can still accept in August.
Explain legitimate differences where the client will see them
There are good reasons for two offices to quote different prices. Getting people and equipment to a remote site costs money. One visit might involve a short drive from the local office. Another might involve flights, accommodation and two days of travel. If travel accounts for the difference, show how you have allowed for it. Otherwise the client is left trying to work out why a drafter suddenly costs more per hour.
Check the conditions as well as the numbers. Two proposals can offer the same hourly rate and still give the client quite different deals. Does one include a senior engineer’s review? Does the other charge separately for it? Has one office agreed to a spending limit and to seek approval before exceeding it? The Australian Government’s guide to preparing quotes is a handy simple reference when deciding what to spell out in the offer.
Read the two offers side by side
Before you send the bid, put its pricing page beside the most recent offer for comparable work. For each difference, ask the person who priced the job to explain it. “We’ve allowed for a senior drafter because these drawings need to be issued for construction” is an answer you can discuss with a client. “That was the figure in my spreadsheet” is a reason to go back and check.
When the job is won, take the accepted pricing schedule to the bid handover. If you included travel in the hourly rate, tell the project manager and the person preparing the invoices. You don’t want the client who accepted your explanation of the higher rate to find a separate charge for travel on their first invoice.
Lesson: Be ready to explain the difference
I’d rather have another project manager ask me about a $20 difference before the bid goes out than have the client ask me afterwards. Keep your contract rates consistent for comparable work. Where the work or the conditions justify a different price, put the reason in the proposal. Don’t make your client ring you to find out, if it gets that far, you are already on the path to losing the job.