Don’t Email Messages to All

Although this is an organisation issue, not just a project issue, it is important to make sure your team does not send messages to all for something that is specific …

Read more

Confirm Meetings

If you (or others) are to travel for meetings, confirm that they have been scheduled. Projects with committees or bureaucracy may overlook setting the times or places and informing everyone …

Read more

Seasonal Influences

Consider seasonal influences on construction. Wet/dry season, snow, monsoon, etc. Be prepared for this and plan accordingly, with allowance for unexpected weather.

Clients Funding

Check the funding sources of your clients. Especially local council clients who rely on funding that often changes.

Check Geotechnical Reports

Check and confirm geotechnical reports that are supplied to you in a contract. The client may supply reports that are old or inaccurate. Specify in the contract that you are …

Read more

Manage the Priorities

Manage the priorities of your projects. Consider them in relation to other projects, business lines in the organisation, geographic areas, and functional managers.

Estimating Design Time

Get to know the usual time schedules for producing plans, drawings, and designs in your organisation. Estimates may be 2 weeks but people with experience in the organisation may know …

Read more

Eliminate Unnecessary Features

Eliminating unnecessary features in design will give the largest savings in a project. If your client wants costs cut, look for the most costly features (in design cost and construction …

Read more

Learn to Say No

You must learn to say no to some requests from clients If change requests from the client will make the design unsafe or unusable, you should refuse to change it. …

Read more

Reward System for Ideas

Some companies have idea boxes or systems for employees to share their ideas for improving an organisation or project. Yet they can often find it difficult to get people to …

Read more