Regular Projects Review Meetings

Your company should have regular projects review meetings. This should include all the head project managers, production managers, installation managers, purchasing manager, tender manager, etc. The aim of this meeting …

Read more

Avoid Bias

When you are making important decisions or preparing designs, get a second opinion on them before acting, because you may be coming from a biased or primed attitude. (Primed is …

Read more

Approval Time Limit

Make sure that the contract specifies the length of time allowed for approvals or decisions. When drawings or documents are sent to the client for approval, you need to know …

Read more

Construction Stage Services Costs

Design engineer under pressure by construction

Construction stage services cost more if the design is still being done when construction begins. Target all the design to be done before construction begins. If that is not possible, …

Read more

Time Charge Codes

Send time charge codes with meeting and function invitations. If you send an invite/schedule booking to team members for a meeting, staff function, training etc, you should send the time …

Read more