How much time should it take to get a document signed?
The review might need an hour. Perhaps the decision needs a discussion. But once those things are done, why does getting the signatures sometimes take another week?
I once worked in an office where I had to walk every document needing approval around to each signatory. If someone was elsewhere, a formal document might need to be posted to them. Otherwise, I would email a scanned copy containing the signatures collected so far.
It wasted a lot of time and created duplicates and partially signed documents. Finding out who still needed to sign became another job in itself.
Meanwhile, the project was waiting.
Problem: Too Much Project Time Is Wasted Chasing Signatures
The paperwork takes longer than the decision
Projects need approvals for purchase orders, variations, drawings, budget changes and many other documents. Those approvals matter. The problem is the administration surrounding them.
Someone prints a document, signs it, scans it and emails it back. The next person repeats the process. Someone else signs the original attachment instead of the version containing the earlier signatures. You now have two incomplete copies.
If the approver is travelling or working at site, the document may sit untouched until they return. You spend time asking whether it arrived, whether it has been reviewed and when it will come back.
Across a busy office, coordinating approvals can become a substantial part of someone’s job. That person could be doing much more useful work.
Delayed signatures affect the project schedule
A purchase order waiting for approval can delay an equipment order. A variation awaiting authorisation can leave a contractor uncertain about whether to proceed. An unsigned handover can leave responsibilities unclear.
The administrative delay may be much longer than the time needed to assess the request. Yet the project still carries the consequences.
Poor visibility makes this worse. “It is with management” does not tell you who has it, what they need or when they will decide. You cannot plan reliably around an approval process that nobody can explain.
Copying a signature creates another problem
A common shortcut is to copy someone’s signature from an old document and paste it onto a new one. Sometimes the instruction is simply, “Use my signature from the last one.”
That image, by itself, does not establish that the person reviewed this document, approved this revision or authorised this particular commitment. If the file is stored where other people can access it, they can reuse it too.
A signature image can form part of a legitimate electronic signing process. The problem is treating the image alone as sufficient evidence of approval. Your project needs a reliable record of the person’s decision and the document to which it applies.
A copy of a signature inserted into a document could be breaking your company policies or could break the law, and it doesn’t prove the person actually approved the document. It can effectively become fraud.
Solution: Use a Digital Signature System and Clear Approval Workflows
Understand what type of approval you need
Get your organisation to implement an electronic approval and signing system that suits its work. First, be clear about what you need it to do.
An electronic approval might be an authorised person clicking “Approve” in the project or finance system. For an internal request, that may be all the organisation requires, provided the decision and supporting document are properly recorded.
An electronic signature is a broader way of indicating agreement electronically. Depending on the process, the signer might type their name, draw a signature or use a signing platform.
A digital signature, in the technical sense, uses a digital certificate and cryptographic methods to link the signature to the document and help detect changes. Adobe’s overview of digital signatures explains this certificate-based approach.
People often use these terms interchangeably. Ask what is actually required. A platform’s completion certificate or audit report is also different from a signer’s digital certificate. Do not assume every electronic signature uses the same identity checks or security controls.
Agree on the rules before choosing the software
Start with the documents your team regularly needs approved. Identify the approvers, their authority and any client requirements. Decide which requests need a signature and which can use a recorded approval.
Confirm the accepted method before sending important documents. In Australia, the Attorney-General’s Department explains that electronic signatures can be valid for most Commonwealth processes, subject to applicable conditions. A particular platform is not universally required. Consent, identification, intention and appropriate reliability is what matters.
State and territory laws and document-specific requirements also need consideration. Get the appropriate advice for your contracts and documents rather than assuming a software subscription settles the question.
Your organisation should establish these rules centrally so each project manager does not have to work them out again. But if your organisation doesn’t have a standard process or system defined, then put the project-specific arrangements and links in your project management plan.
Don’t go down a rabbit hole in choosing the right software, if you don’t already know, check if your organisation already has a chosen and available system that your team should all use.
Give each approver a clear purpose and authority
Decide who prepares, checks, recommends and authorises each type of request. Those are different responsibilities, even when the same form records them.
For example, an engineer may confirm that equipment meets the specification. The project manager may confirm the scope and budget. A person with the required financial delegation may authorise the purchase.
Make those roles clear beside the approval fields. A general “Approved” box can be ambiguous if people mean different things when they select it.
Check the amount and type of commitment against the person’s authority, as discussed in Delegation Limits. A signing system can record a signature accurately while the signer still lacks authority to make that decision.
Include the project manager in the purchase approval process where required. If project purchases go only to an employee’s line manager, the project manager can lose visibility of commitments against the budget.
Prepare one complete document for approval
Finish the necessary reviews before issuing the document for signature. Check the project number, document reference, revision, amount and attachments. Make sure the request explains the decision needed and the consequences for cost or time.
Put the essential information near the start. An approver should be able to understand the request without searching through several attachments, while still having access to the supporting detail.
Identify exactly what the approval covers. For a drawing package, list the drawing numbers and revisions. A vague approval of “the drawings” leaves room for disagreement about which drawings were included.
Once issued for signing, keep that version controlled. If the substance changes, withdraw or supersede the request and obtain the necessary approvals for the revised document. Do not carry signatures across to altered content as though the earlier decision automatically applies.
Route the request through a simple workflow
A practical process could work like this:
- The originator prepares the document using the current template.
- The system sends the request to the required reviewers and approvers.
- Each person accesses the document using the agreed identity checks, reviews it and signs, approves or returns it with comments.
- The system records each action and shows what remains outstanding.
- Once all required steps are complete, it notifies the relevant people and stores the completed record.
Use sequential steps where one approval depends on another. Use parallel reviews where people can review independently. There is little benefit in making five independent reviewers wait for each other simply because paper used to move around the office that way.
Keep signing after any reviews that may change the document. Give people a clear way to reject a request or ask for corrections. A workflow must handle an actual decision, including “no”.
Set up access and train people properly
Tools such as Docusign or Adobe Acrobat Sign are examples of systems to assess. Your organisation may already have an approved signing service or workflow tool, so check before introducing another one.
Select the capabilities needed for your documents, including authentication, routing, reminders, audit records and export. Confirm which features are included in the proposed plan and configuration.
Set up users before an urgent approval is needed. Where supported, integration with the organisation’s single sign-on can reduce repeated login steps. Keep the authentication appropriate to the risk, including multifactor authentication where required. Staff and external recipients may have different access arrangements.
I have been in teams where people became stuck at the sign-in step and returned to printing and scanning. A licence does not solve that problem. Help each person complete a practice request using the process they will actually need. If the approval process keeps getting stuck at a certain person and they revert back to physically printing and signing the document, you have lost most of the benefit of the digital signatures. Figure out what their problem is, fix their sign-in issues, and train them properly so they can approve the documents as easily as they should be able to.
An administrator can prepare and issue a request. The approver should still make their own decision using their own authorised access. Sharing credentials or copying a signature is a poor substitute for getting the setup right.
Make outstanding approvals visible
The originator should be able to see who has completed their part, who is next and which requests are overdue. Relevant approvers should receive confirmation when the process is complete.
Set realistic response periods and include approval time in the project schedule. Faster transmission does not remove the time needed for technical review or a management decision.
Use reminders and an agreed escalation process. If a request remains unanswered, someone should investigate the reason. Repeated reminders will not fix missing information or an incorrect recipient.
Plan for leave and staff changes. An authorised delegate should act under their own identity, with the delegation recorded. Forwarding a signing link does not, by itself, grant someone authority.
Keep a named process owner responsible for maintaining the workflow, recipient roles and escalation arrangements. Otherwise, requests can continue going to someone who left the organisation months ago.
Keep the approval evidence with the project records
Store the completed signed document and its supporting audit record in the agreed project location. Depending on the system, this may be called a completion certificate, transaction history or audit report.
For example, Docusign’s Certificate of Completion guidance describes records of signing events, timestamps and identifying information, including IP addresses. An IP address is supporting information; it is not conclusive proof of a person’s identity.
Check what your chosen configuration actually records. Retain the original signed electronic file so its verification information is preserved. Printing and rescanning it does not preserve that information in the same way.
Connect the approval to the relevant purchase order, variation or decision register. Someone taking over the project should be able to find the decision and the exact document approved without access to your personal inbox.
This belongs within a simple document system, with appropriate access and retention arrangements. Check that records remain accessible if a staff member leaves or the organisation changes software.
Start with a common form and measure the benefit
Choose a frequently used form that causes unnecessary work. Map the current process, remove redundant steps with the process owner and trial the electronic workflow with a small group.
Test an ordinary approval, a rejection, an absent approver and a request needing correction. Include an external signer if that is part of normal use. Check that the completed record can be found and opened afterwards.
Measure both staff effort and elapsed time. Saving an hour of administration is different from shortening the approval cycle by three days. Both can help the project, but they should be reported separately.
As an illustrative example, suppose an office processes 100 forms a month and spends 30 minutes per form distributing, chasing, scanning and filing them. That is 50 hours of administration. Reducing this to five minutes per form would save about 41.7 hours a month, or 83% of that administrative effort.
The calculation excludes the time needed to review the documents. It also excludes software, setup, training and ongoing support costs.
I would expect very large coordination savings where the existing process is particularly cumbersome. A 90% reduction might be a useful target to test, but I would not promise it without measuring the starting point and trial results.
Connect signing to the rest of the process
Consider what happens after the last approval. Does procurement receive the authorised request? Is the project manager notified? Is the approved amount recorded against the relevant commitment?
Where practical, connect these steps so people do not have to download a signed document, rename it, email it elsewhere and retype the same information into another system. This is another useful application of automating project management where possible.
Removing repeated printing and scanning saves paper and ink and can reduce unnecessary email attachments. Actual storage and bandwidth savings will depend on the files and retention settings. The more useful measure is whether the team spends less time moving documents around and can reliably find the completed approval.
Lesson: Make Approvals Easy to Complete and Easy to Prove
Your project should not need someone walking around the office, sending repeated emails and assembling partially signed copies every time a document needs approval.
Use an electronic approval or digital signature system suited to the documents and the organisation’s requirements. Give people clear authority, a complete document to review and a straightforward way to record their decision.
Train the team, monitor outstanding requests and keep the completed records where the project can find them. Start with a common form and measure the improvement before extending the process.
The time needed to make a sound decision is worthwhile. The time spent chasing paper usually is not. Make it easy for people to give the approval your project needs, and make sure you can show exactly what they approved. And if people don’t know how to use the process, or don’t bother trying, train them how to do it. Don’t accept excuses. If the process will save time, it should be used by the whole team.