Can you book the surveyor for Monday?
It’s Friday afternoon. Your client rings with good news. They’ve selected your proposal and want the survey crew on site on Monday. The surveyor has one crew available and needs an answer by three. You ask about the signed contract. “It’s with our director. Can you book them in while we wait?”
Before you make that call, ask yourself one question. If the director decides on Monday to postpone the project, who pays for the survey crew?
Problem: Your costs can start before the client has committed
From your client’s point of view, they’ve asked you to keep a date free. From the surveyor’s point of view, you’ve booked two people and a vehicle for the day. Both interpretations are quite reasonable. The trouble is that your company is in the middle, and the surveyor will send the invoice to you.
Much the same thing can happen inside your office. You ask a designer to “just get started” with the drawings. By the time the client sends back the contract, the designer has spent two days on an option the client has removed from the scope. Which part of the revised fee will cover those two days?
It can be harder to ask for a signed contract when you know the client well. You might trust their project manager completely. They might also need someone else to approve the expenditure. Ask about the client’s delegation limits while you’re discussing the proposal, when there’s still time to get the right person involved.
Solution: Get a signed contract before you release the work
Check what both parties have signed
Before you give the team a start date, check that authorised people from both organisations have signed the same version, including the agreed scope, fee, deliverables and payment terms. Check the attachments too. If you priced revision C of the scope and the client attached revision B, sort that out before signing. This is the point to agree with the contract before signing it.
Read the commencement clause. If the contract requires a separate notice to proceed, wait for that as well. Save the signed contract and any start instruction together in the project folder. Then tell the team which activities they can start and when. That saves the designer having to guess what “we’ve won the job” means.
Give the subcontractor the same certainty
When you engage the surveyor, you’re now on the client side of the arrangement. Agree in writing on the work, fee and applicable terms, and have both parties sign before the crew mobilises. Include a right for your company to terminate the subcontract. Check what notice you must give and what you’ll owe for work done or costs already committed. If the client cancels, you want to know whether you can stand the crew down and what that phone call will cost.
If those terms are unclear, arrange a legal review of the contract. The Australian Government’s guide to preparing a contract also covers payment arrangements and how to end a contract.
If only the survey is urgent, authorise only the survey
Suppose missing Monday means waiting three weeks for another crew. Give the client a choice. They can move the survey date, or you can both sign a short agreement for the survey while the main contract is finalised. Set out the site, the survey deliverable, the fee or rates, a maximum amount and an end date. Agree how your company will be paid if the wider project never proceeds.
Then give the surveyor a matching written instruction, signed by both parties. For example, approve one site visit and a survey plan up to $4,000 in total. If the surveyor finds that a second visit is needed, ask for the cost and get the extra work approved in writing before booking it. Tell the design team their work is still on hold.
If your company still wants to start without written client approval, take the decision to the most senior appropriate manager with authority to accept that risk. Show them the dollars at risk, including staff time and cancellation charges, and record their decision and spending limit. Their approval means your company has chosen to carry that cost if necessary. You still need the client’s agreement to be confident of recovering it.
Lesson: Know who has agreed to pay before you say yes
Make sure you get a signed agreement before work is started on the project.
Get written agreement to all terms and conditions.
I’d get a signed contract before committing the team or a subcontractor. If Monday genuinely matters, pick up the phone while there’s still time to sign for the survey. Then you can give the crew a firm answer, and everyone knows exactly what that answer covers.
Remember that the risks on a project are substantially increased by not having a signed written contract.