“Can you make the slab a metre wider while you’re here?” The client’s maintenance supervisor is standing beside the formwork. He explains that once the pump is installed, his crew will need somewhere to put the motor when they lift it out for servicing. It’s a good point. The concrete is due tomorrow morning. Your site supervisor rings you. What do you tell him?
Problem: Everyone thinks they know the project scope
Ask the designer what the slab is for and she’ll tell you it supports the new pump. Ask the maintenance supervisor and he’ll tell you it has to give his crew enough room to service the pump. Both answers make sense. The trouble starts when everyone assumes those answers describe the same slab.
You might remember agreeing to provide maintenance access. Do you remember how? Perhaps the approved layout shows a separate hardstand beside the slab. Perhaps the brief requires space to lay down the motor and the designer missed it. Or perhaps operations has only just identified the need. Each possibility calls for a different answer. If you promise a variation before checking, you could be asking the client to pay twice. If you tell the crew to go ahead, you could be committing your company to redesign and extra work at its own cost.
Solution: Put the project scope to work
Read the documents behind the drawing
Start with the signed contract, the scope and specifications it refers to, and any approved changes. Find the wording that answers the question in front of you. A dimension on a drawing tells the concreter where to put the formwork. It won’t necessarily tell you what maintenance access your company agreed to provide.
When you take on a project, put a short scope summary in your project management plan. Record the main deliverables, the work others will do and the documents that give the detail. Add the relevant drawing number or clause beside anything likely to cause confusion. A note such as “client to construct the adjacent hardstand before commissioning” gives you something useful to follow up. “Maintenance access by others” still leaves you guessing who to ring and when you need it ready.
Ask the people who will do and use the work
At the kick-off meeting, put the layout on the table. Ask the client’s maintenance supervisor to show you where the motor will go. Ask the designer to point out where that space is allowed for. Then ask the contractor which surfaces are included in the price. You’ll learn more from those three answers than from asking a room full of people, “Is everyone clear on the scope?”
Give the drafter, contractor and client representative a record of what you agreed. If two documents disagree, give someone the action to resolve it and set a date before the affected work starts. Clarifying who is responsible for each part of the work is particularly important at the point where one contractor’s work finishes and another’s begins.
Check again when someone wants a change
Back at the formwork, ask the supervisor to hold the affected work while you check the requirement with the designer and the authorised client representative. Tell them when the concrete is booked and when the crew needs a decision. If the agreed project scope already includes the maintenance space, work out how to meet that requirement. If the client wants a larger slab as an addition, explain the effect on design, cost and tomorrow’s pour. Follow the contract’s variation process and get the decision in writing before instructing the crew. Small requests like this are an easy way for scope creep to get started.
Once a change is approved, get the revised drawing to the people doing the work. Check that the supervisor has replaced the old site copy. An approved variation sitting in your inbox does very little for a concreter holding yesterday’s drawing.
Use AI to Speed of the Search Process
If you have access to an AI assistant at work, make use of it regularly to check if something raised or mentioned is in the scope (and where). AI is not perfect, but a quick question such as “show me where the concrete slab for the pump is mentioned in the scope.” In seconds you will be pointed to the exact location and you can check the nuances of that section, rather than spending many minutes or hours going through it manually.
Lesson: Read the scope more than once
Revisit the project scope before you brief a new contractor, release a drawing or hand the project to another manager. If the client changes project managers, walk the new person through the current scope and the decisions that changed it. My test is simple. Could your replacement answer the supervisor’s phone call, find the document that supports the answer and tell the crew what to do next?
Know the scope of your project. Read it often. As a project manager it rules your role on the project.