“Can you send us the updated drawings on Friday? Operations have finished their review.” Your designer issued the final drawings last month and has moved on to another project. You thought the review was finished. The client thinks you still owe them a set of drawings.
You open the contract. The closest thing you can find to a description of your contract duties is “liaise with the client and finalise the design”. Would you ask the designer to start work, or would you ask the client to approve a variation? What wording would you point to when the client asks why?
Problem: The estimate says more than the contract
Your estimator allowed for six drawings, one review meeting and one final issue. The client’s engineering team usually reviews drawings first, then sends the revised set to operations. Each group expects its comments incorporated. Both parties have a reasonable idea of what it takes to finish the design. Unfortunately, they’ve allowed for a different number of reviews.
If the detail stayed in the estimating spreadsheet, the client had no opportunity to question it. Telling them you’ve used up the design hours won’t settle the matter. You can run over budget doing work you agreed to do. You can also have hours left when the client asks for something extra.
The same problem turns up on site. Take “site inspections as required”. Your engineer has priced two visits. The client expects a visit each time the contractor finishes a section. If the contractor builds eight sections, who pays for the other six visits, the travel and the reports?
You don’t have enough detail in your proposal and in the written contract, so your project contract duties are unclear.
Solution: Write contract duties both sides can price
Check the scope against the fee
Put the draft contract beside the estimate. For each significant allowance, find the words that tell the client what they’re buying. If you’ve priced two site visits, identify the stages you’ll attend, what you’ll inspect and what record you’ll provide afterwards. Then work backwards through the client’s brief. Can you find an allowance for everything you’ve promised?
Look closely at the deliverables. Six PDFs might be all the client needs. If they also want editable drawings in their own template, your drafting lead may have to allow time for conversion and checking. Ask for a sample before you agree on the fee. That’s the sort of detail worth settling in the specifications.
You need strong, clear language in the contract documents so that your company’s duties are very clear.
Give the client a duty as well
For the drawing review, I’d want wording along these lines, with dates and quantities that suit the job.
“The consultant will issue the six drawings listed in Schedule A as draft PDFs. The client’s project manager will collect comments from engineering and operations and return one consolidated set within ten working days of receiving the draft. The consultant will address the agreed comments and issue the six final PDFs within five working days of receiving that set.”
Now ask the client’s project manager whether operations can work to that arrangement. Perhaps operations needs to see a revised design before it can comment. If so, include the second review in the scope, fee and program. At kick-off, give the designer the agreed drawing list and review dates. The person answering the client’s call needs to know the scope of the project too.
Use the contract duties to assess a new request
Suppose the comments arrive after the final issue. One says drawing four shows the wrong pump model. You check the agreed equipment schedule and find your designer made an error. Arrange to correct it. The client paid for a drawing showing the specified pump.
Another comment asks you to move the pump to make room for a future extension. That could mean revising the pipe supports and electrical layout too. Explain the effect on cost and timing, identify who can authorise the change, and follow the contract’s variation procedure. The Australian Government’s Prepare a contract guide covers what to include when setting up that procedure.
Once the client decides, tell the designer which comments to action. If the move goes ahead, document the change in scope and give the checker the revised layout. Otherwise, someone checking against the original brief could quite reasonably ask the designer to move the pump back again.
Lesson: Ask both sides what the fee buys
Before signing, pick one duty that could use up a fair bit of your fee. Ask your estimator how many visits or drawing issues they’ve priced. Ask your client how many they expect. A difference of six site visits is much easier to resolve across a tender table than it is when your engineer is already on the road.
Write the answer into the contract duties and give it to the people doing the work. When the client rings on Friday, you and the designer should be able to open the same document and explain what happens next.
Your scope should be specific, clear, and understood by both parties in the contract.