Turn Potential Enemies into Allies

For controversial or difficult projects, turn potential enemies into allies by including them in the project team. They may come up with better ideas to get the project done, and …

Read more

Paperwork in Big Companies

Remember that the larger the organisation you work in, the longer it will take to get paperwork processed. This is not always the case, but extra time needs to be …

Read more

Review Test Results Early

Review test results before samples are destroyed. It is too late to get them retested later if they have already been destroyed or disposed of. It is best to review …

Read more

Do Any Training Offered

Take up offers or opportunity in any training offered by your company or by a head contractor. Benefits include: Increases your skills and abilities. Gives you recognition within your company. …

Read more

Make Contractor Responsible for Site Safety

If your company is not involved with construction (but just design or inspection), make sure the contract states that the construction contractor is responsible for site safety, not the “engineer” …

Read more

Map Soil Testing

For soils testing, get a map and list of where tests were taken so that you can see if that matches where your designs are to be constructed. Some soils …

Read more

Directing Consultants

If, in your contract, the client instructs you to directly pass on the cost of consultants, it would be better to have the consultants contract directly with the client instead …

Read more

Document Reliance on Information

In a contract, your company should make sure the document indicates that you will rely on information and materials supplied by the client. E.g. surveys, soil tests, reports. If the …

Read more

Visit the Intended Site

Visit the intended project site before submitting the tender bid. By doing this you can spot potential problems that may not have been documented. Do not do a cost proposal …

Read more

Document Design Changes and Delays

You should document (in writing) any design changes or delays caused by the client. This is very important for claiming cost or time extensions. A good change management system is …

Read more

Design Discrepancies

If your company is the design contractor but not involved in the construction phase you should instruct the client to notify you for your company’s input for any design discrepancies. …

Read more

Do Regular Design Reviews

Your company should have a set time or point that reviews of the design process are carried out. Often at stages like 30%, 60%, 90%, 100%. You should do this …

Read more

Check References

Always check references given to you and also that you are submitting. You should check that references you list for your company will in fact give you a good reference. …

Read more

Legal Review of Contracts Before You Sign

Legal Review Of Contracts concept with magnifying glass over contract terms. - myprojectlessons.com

An acceptable price and scope do not mean the contract is acceptable. Arrange legal review before making commitments, allow time to negotiate terms, and check liability, insurance and the promises your team will have to deliver.

Read more

Document Changes in Scope

If, during a project, the client realises a mistake in the scope or specs or one is pointed out to the client and the client authorizes or instructs a change …

Read more

Isolation and Lockout Procedures

Always make sure that isolation or lock-out procedures are followed. If an electrical contractor needs to access some wiring, they should follow a procedure of isolating or de-energizing the circuit. …

Read more