Why Projects Need Quality Assurance and Quality Control

First Published:

Last Updated:

Suppose your client rings and asks, “Who checked the drawing you sent us on Friday?” You open the project folder. There’s a signed check sheet for Revision B and a set of comments marked up in red. Then you look at the drawing you actually sent. It’s Revision C. The engineer who issued it is on leave. What are you going to tell the client?

That’s a good question to ask about quality assurance on your project while everyone is still around to answer it. Pick a drawing your team issued last week. How long does it take you to find out what changed, who checked it and whether the client received the checked version?

Problem: The Quality plan is on file, but the checks are missing

A project manager can get a quality plan submitted on time and still have very little idea how well the team is following it. The plan might call for an independent design review. The program shows a single activity called “complete design”, with the review, corrections and approval all due on the same Friday. When the design takes until Thursday afternoon, whose time do you think gets squeezed?

A signature can give you false confidence, too. In the drawing example, the engineer may have made every correction the checker requested. They may also have moved a pipe connection while making those corrections. The earlier signature tells you what the checker saw at Revision B. Someone still has to decide what needs checking on Revision C before it goes out to the client.

It gets harder when part of the work is done by a subconsultant. Your drawing might use dimensions from their equipment layout. If they revise the layout and your team issues a drawing based on the earlier dimensions, both companies can have a signed drawing on file and the two parts still won’t fit. As far as the client is concerned, your company delivered the package. You’ll be the one organising the corrections and explaining the delay.

Solution: Plan the reviews and check the work

Give quality assurance and quality control different jobs

Quality assurance (QA) gives you confidence that the team has a suitable way of meeting the project requirements and follows it. For a drawing package, that might mean agreeing how revisions are reviewed, assigning an independent checker and auditing a sample of issued drawings to see whether the process works. The American Society for Quality explains the distinction in more detail.

Quality control (QC) is what the team does to check the actual work against those requirements and deal with defects. For the same package, the checker compares the connection dimensions on the drawing with the current equipment layout, marks up a discrepancy and checks the correction. That check can catch a costly mistake. An audit can tell you whether the other drawing packages are getting the same attention.

Put review time in the program and the fee

Start with the contract. Which plans must you submit, who reviews them and when are they due? Which deliverables need client approval or a witnessed inspection? Put those dates in your project management plan and program. Name the person who will do each review (or at least the title and role of the person if the work might be swapped to a different person), allow for their time in the budget and give the author time to make corrections. A client submission date is a poor choice for your first internal review.

Match the reviews to decisions the project will make. On a design job, you might review the layout at 30% design while there’s still room to move equipment, then check dimensions across disciplines at 60% before people spend time detailing the connections. For a short report, a single technical review and a final issue check might be enough. Agree what each reviewer is expected to look for. “Please review by Thursday” leaves a lot to interpretation.

Keep the evidence with the deliverable

Make it easy for the next person to follow the job. For a drawing, keep the drawing number and revision, the marked-up copy, the author’s responses and the checker’s sign-off together. Record which comments are still open and who can authorise issue. If the revision changes after sign-off, identify what changed and get the affected work checked again. A simple verification system for deliverables can do this without asking staff to enter the same details in three places.

Timing matters even more on site. If reinforcement has to be inspected before a concrete pour, agree who will attend, how much notice they need and who can release the hold point. Record the location and drawing revision at the inspection. Next week, when the reinforcement is under concrete, it will be too late to send someone back to witness it. See Inspection and Verification of Construction Works for the practicalities of witnessing and sign-off.

Include subconsultants and subcontractors

When you engage a subconsultant or subcontractor, agree what quality records they will provide and when you can review their work. Ask for their project quality plan early enough to resolve differences with yours. If their process ends when they issue an equipment layout, who checks that your team has picked up their final dimensions? Put a name against that task on your side as well.

At the first submission, ask for the check record for one item you intend to rely on. Compare it with the deliverable you received. If the record refers to a different revision, resolve it then, while the people who did the work can explain it. Repeat these checks where the work is critical, the team changes or an earlier review has found a problem. Keep the results with your own audit records so you can show the client how you monitored the work.

Run an internal audit while there’s time to fix things

Book the first internal quality assurance audit during project planning. I’d schedule it soon after the first significant deliverable. By then there’s real work to examine and the findings can still improve the next submission. Ask someone independent of the work to pick an issued item and trace it from the client’s requirement through to the copy the client received.

Document what the auditor sampled, what they found and where the evidence is. If a check was missed, deal with the affected deliverable first. Then find out why it happened. Perhaps the checker signed before the subconsultant’s final layout arrived. Give someone responsibility and a due date to change that sequence. At the next review, look at a newer drawing to see whether the change worked. That last step gives you a reason to close the finding.

Lesson: Assume the client will ask

Even if your client has never audited one of your projects, you should make the assumption that they will. Allow time for quality assurance in the program, check the deliverables as they are produced and include the people doing work on your behalf. Their work carries your company’s name when you send it on.

Try the Friday drawing question at your next project review (“Who checked the drawing you sent us on Friday?”). If someone can open Revision C, show what changed and bring up the record of who checked those changes, you can answer the client while they’re still on the phone.

Doing all this will make client audits of the project much smoother and easier.