How to Document Changes in Scope So Your Team Builds the Right Thing

First Published:

Last Updated:

The truck arrives with a three-metre gate. The site supervisor takes one look and says, “That was supposed to be four metres.” The project manager can produce the client’s written approval for the wider gate. The purchasing officer can produce the specification she used to order it. They’re both holding project documents. Which one is going to help you fit a three-metre gate across a four-metre opening?

Problem: The client approved the change, but the team still has the old scope

It’s easy to think you’ve done your job once you document changes in scope and get the client’s approval. In the gate example, imagine the client spotted an error in the original specification. The access drawing showed a four-metre opening, but the gate schedule said three metres. The designer corrected the schedule and sent it to the project manager. Unfortunately, the purchasing officer had printed the tender set weeks ago. Why would she go looking for a new gate schedule when nobody had told her the old one was wrong?

Now you have a gate to return, a supplier who made exactly what you ordered, and a site crew that may have to come back another day. You could forward the approval email to everyone this morning. It would have been considerably cheaper to check one purchase order last week.

Solution: Document the change in full and follow it through to the work

Start with what the client actually agreed

Find the relevant clause, drawing or schedule and compare it with the request. In this example, two documents already disagree. Ask the authorised client representative to confirm the required opening and the specification to use. If the original documents both called for three metres and the client now wants four, price the extra work and check the delivery date before promising either.

Write down exactly what changed

“Client approved a wider gate” might make sense to everyone who attended the site meeting this morning. In six months, could another project manager use that note to check a payment claim? Which gate was it? How wide did the client want it? Even the word “width” leaves room for a costly mistake. The width of the gate leaf and the clear opening between the posts are two different measurements.

Give the change a reference and record enough detail for someone who missed the discussion to act on it.

  • What changed and why. Identify the item and record the previous and approved requirements together. For example, “Front vehicle entrance, item G1. Revise the gate schedule from a 3.0 m clear opening to a 4.0 m clear opening between posts to match the approved access drawing.”
  • Who authorised it and when. Name the person who raised the discrepancy and the authorised representative who decided it. Record the date and link to the written instruction. If the instruction came by phone, send your understanding back and obtain the confirmation required under the contract.
  • What the decision covers. Record the effect on price, delivery and work already ordered. If the supplier confirms the same price and delivery date, say so. If the supplier is still checking, write “cost pending” and name the person who will follow up. A blank space could mean either.
  • Which documents give effect to it. Link the instruction to the revised gate schedule, the affected purchase order and the supplier’s acknowledgement. Keep the earlier issue so you can show what the purchasing officer had when she placed the order.

One change register entry with links to the approval and revised documents can be enough. Even when the price stays the same, document changes to the scope brief so the team can see exactly what it has agreed to deliver.

Put a correction in every working copy

Give the corrected gate schedule a revision number and date. Identify the changed line and reference the client’s instruction so the next person can see why it changed. Keep the signed original and the earlier issue in the project record. Put the approved revision where people go to get the current specification.

Then follow the old copy. Who received it? The designer may work from the shared folder, but the purchasing officer has a printout beside her keyboard and the site supervisor has a PDF saved on a tablet. Replace or clearly mark the superseded pages in each working set, including the copy in the site office. Send the supplier the revised schedule if they already have the old one. These are the practical details of project document control.

One question is worth a phone call here. “Have you placed the order yet?” If you have, ask the supplier to confirm whether fabrication has started and what it will take to amend the order. Updating the project folder won’t change a purchase order that’s already gone out.

Give additional scope a place of its own

Suppose the client also asks for a second gate at the rear access. You can fix the width of the first gate by correcting a line in the schedule. A second gate brings a different set of questions. Does the price include new posts, footings and installation? Who will supply the lock? When will the crew have access?

Give the addition its own variation reference. Set out the agreed inclusions, exclusions, price and timing, and file the written approval with it. Keep approved additions together in a shared location the team can access, with a matching hard-copy set where the site needs one. Reference the variation in the current gate schedule and issue the affected drawings. Someone pricing the job next month should be able to start with the original scope and find every approved addition. The Association for Project Management’s guide to change control explains how to track a request through assessment, decision and implementation.

Check what the team is about to do

At your next progress meeting, look at the approved changes alongside the work coming up. For the front gate, check the width on the supplier’s order acknowledgement. For the rear gate, check that someone has ordered the posts and allowed time for the footings. Keep pending requests visible with their status so the crew knows which work can proceed. Repeat the check before procurement, construction or handover, while there is still time to fix a missed instruction.

Lesson: Check the record, then check the working copy

When you document changes in scope, ask someone who missed the meeting to read the entry. Can they tell you what the client originally required, exactly what changed, who approved it and what it means for cost and time? If they have to ring you to find out what “wider gate” means, the record needs more detail.

Then ask the purchasing officer to show you the gate on the supplier’s order acknowledgement. Does it specify the approved four-metre clear opening? That last check tells you whether the decision you carefully documented is the gate you’re actually going to get.

Leave a comment