Projects often share the same people, equipment and suppliers. Regular projects review meetings help managers coordinate resource needs, identify delays and share problems that could affect other projects. Keep them brief, practical and focused on decisions and actions.
Bid teams / tender teams often bid for projects that the company can’t do. They will make a schedule that is too tight, or have milestones that are impossible to …
Put risk activities in your schedule (plan). Your client is more likely to accept allowances for risk if you can show how it is worked out, how long it is …
Make sure every document you create has the file path and file name in the header or footer. This will mean that all printouts will show where the file was …
Check if “unsuitable” soil/fill is really contaminated. It might me that it was just wet or not compact-able. It may not be contaminated. Avoid paying for removal of “contaminated” material …
A good project reporting system connects costs, labour, forecasts and billing so reports can be produced with less manual work. Set it up early, give the team clear responsibilities, and use the same information for project and program reporting.
Keep track of and in contact with colleagues, former colleagues, industry contacts, old friends in similar or related industries, clients, former clients, uni friends, etc. This can help getting introductions, …
Make sure your team members know their roles, job description, and what they should be working on. You as the project manager or line manager should define and clarify the …
Get certificates that are required for your job. This will save you time, and enable your company to place you on projects immediately if you are selected (without having to …
If you are in the water industry or an industry that deals with pipes, valves, or pumps then make sure you have a copy of the pipe sizes available, internal …
Join PMI (Project Management Institute) and use the PMI Compendium of Project Management Practices This is a good guide for new project managers or PM’s in an organisation without a …
Finishing the work is not the same as delivering it. Check the payment milestone, submit the required package and keep the evidence before invoicing your client.
Recognize when you or your team don’t have the expertise to accomplish something and get help. This could be either within the company or from outside experts. Check with internal …
Quality Assurance (QA) and Quality Control (QC) are important. Make sure QA plans are put together and submitted properly. Make sure internal audits are done to be sure the project …
For controversial or difficult projects, turn potential enemies into allies by including them in the project team. They may come up with better ideas to get the project done, and …
Remember that the larger the organisation you work in, the longer it will take to get paperwork processed. This is not always the case, but extra time needs to be …
If a partly completed project is put on hold (deferred project) by the client, when it is restarted it should be treated as a new project. This includes reviewing and …