Document All Client Communication
Important client conversations should not exist only in people’s memories. Document decisions, instructions, commitments and other material communication so your project has a reliable record.
Important client conversations should not exist only in people’s memories. Document decisions, instructions, commitments and other material communication so your project has a reliable record.
Clarify the terms and conditions with the new project manager. If the client changes during a project (or the client project manager changes), then you as the project manager should …
Be wary of low bids by contractors. Get a number of bids. Compare and check why a low bid is so low. If a low bid is accepted, be especially …
It is important in a project to keep very good documentation. It should be complete, organised, and easy to search (not unorganised folders on lots of team members desks where …
Scope creep is sneaky and costly. Learn how to spot it early, manage it firmly, and keep your project from going walkabout with these proven field strategies.
Keep good control of client communication. Ensure all important communications are between the project manager and the client project manager, especially for cost, schedule and scope decisions.
Your client has always accepted one site visit a month. What happens when their new project manager reads the contract and expects you there every week?
If your company is involved in site inspections, site supervision, or site management take lots of photos. Make sure to file these photos by name (location, item) and date. Some …
When buying specialty equipment, make sure the supplier can and will supply a complete system. If they do, take it. Avoid trying to save money by doing parts of it …
Make sure to include a precedence clause in the specifications. You should define which documents or sections take precedence. That way if there are errors or conflicts, one will take …
Make sure drawings have cautionary notes for areas of potential conflict (e.g. electrical wiring near nail fasteners).
Get agreement on the final designs with subcontractors before submitting them to the client. You need subcontractor buy-in to the design. This gives you the opportunity to confirm they can …
I find that having liquidated damages in a contract from my client helps me as a project manager. Companies often want to avoid having liquidated damages in the contract. However, …
Avoid the use of superlatives in contracts and documents. E.g. “all, make sure, assure, insure, as necessary”. These can be interpreted as making a guarantee. It would be better to …
Make sure to allow for inflation in cost estimates. Particularly allow for large increases in raw material costs (e.g. stainless steel, copper). This is important in the tender preparation process. …
It is important to clarify the ownership of drawings your company produces. Make sure the contract or agreements clarify the ownership of drawings and documents. Some clients may expect the …
Your client wants a survey crew on site on Monday, but the contract is still waiting for a signature. Who pays if the job is postponed?
Know the scope of your contract. Read it often. As a project manager it rules your role on that project. Make sure you clarify the scope with all stakeholders to …
How many drawing reviews or site visits does your fee include? Clear project contract duties help you and your client agree on the work and recognise a genuine variation.
Make sure your team has a comprehensive project work plan. This should show details of design assumptions