Check Your Authority

Hand signing a document

Avoid problems later by checking early in the project who is responsible for what aspect of the project and who has authority to approve what. Document this.

Read more

Meeting Your Forecast Budget Spend Rate

Problem: Some projects have budget allocated to them, rather than being funded by a purchase order or contract or similar. This is particularly the case with internal projects or government …

Read more

Evidence for Late Completion

Problem: If not properly managed, some projects you are managing will end up being completed late. Even though there may be legitimate reasons for this, it is your responsibility as …

Read more

Specify the Due Date

When submitting any document for review (such as a design, invoice for payment, report, etc.), specify the date a response is due (perhaps 10 business days). For contractual related items …

Read more

Control of Documents

Keep good control of formal documents. When writing a set of documents, plans, etc, make sure that final production is coordinated by one person, or that the file storage is …

Read more

Datum Differences

Be aware of datum differences when doing coastal projects. Coastal/ocean datums are different to land datums and if not specified correctly could cause problems on a project. You don’t want …

Read more

Evaluation of Tenders

When requesting and evaluating tenders make sure your specifications are very clear about what is required. Also check that the tenderers clearly describe what they offer. When accepting and signing …

Read more